schedule_visits turns each account’s service cadence into a day-by-day plan. Every day is split into tight geographic work clusters (“buckets”), and each bucket is one technician-day kept under an hour cap you set. This page covers the calendar features: start dates, blackouts, fixed appointments, due dates, and weekday rules. It also covers anchoring each day to a technician’s home and a shared depot.
Scheduling decides which day each visit happens. Routing (
calculate_route) decides what order to drive one day’s stops. Use both.
What you need
| Input | Tell the agent | Notes |
|---|---|---|
| Accounts with a cadence column | “Visit frequency is in service_interval_days“ |
Declare it as the visit-frequency column when you load the accounts. Say whether the number is days between visits or visits across the horizon, and which values mean “never visit” (by default 0, empty, or null). |
| Onsite (dwell) time | “45 minutes per visit”, or “use the onsite_minutes column” |
Required. The server never assumes a default. |
| Daily capacity | “8-hour days, hard cap”, or “aim for 7 hours, ±10%” | Required. Use a hard ceiling (not_to_exceed) or a target band. |
| Horizon | “Two weeks”, or “derive it from the longest cadence” | Optional. Defaults to the longest cadence. |
| Start date | “Day 1 is Monday, November 2, 2026” | Required whenever you use dates. Without a start date, days are numbered 1, 2, 3… instead of being calendar dates. The server won’t assume today. |
Calendar rules (visit_constraints)
Each rule applies to one account. Mix as many as you need.
| Rule | What it means | Ways to state it | Example |
|---|---|---|---|
| Blackout (or no-service window) | The account can’t be visited | A single date, a list of dates, a date range, a range that repeats every year, or weekdays that repeat every week | “No visits to store 337 from Nov 9 to 13 (inventory).” “Never on Veterans Day, every year.” “Never on Sundays.” |
| Fixed | A hard appointment on one date | One date | “Inspection at site 184 on Nov 5.” |
| Due | Must be visited by a date, optionally not before another date | Due date, optional earliest date; penalized (default) or hard | “Site 103 between Nov 10 and Nov 12, hard deadline.” |
| Anchor | Fixes when the recurring pattern lands | A date or a weekday | “Site 1383 is always serviced on Tuesdays.” |
| Allowed weekdays | Days the account can be visited | A list of weekdays | “Weekdays only for site 213.” |
Rules always win:
– Blackouts are always hard.
– A fixed appointment counts toward the cadence. It replaces a regular visit; it isn’t added on top.
– Penalized due dates are scheduled as early as possible. Any miss is listed by account with the number of days late. Mark a deadline hard if it can’t slip, for example for a regulatory inspection.
– Conflicts stop the run. If rules can’t all be met (say, a fixed date inside a blackout), the schedule fails with a date-conflict error instead of quietly dropping a rule. Decide which rule moves, then run it again.
Seasonal windows. To allow visits only in certain months (for example, “spring and fall only”), black out the other months with a range that repeats every year. A due date with an earliest date also works for a one-off window such as “between March and June 2027”.
Anchoring days to technicians and a depot
Without technicians, buckets are unanchored day-clusters, and you can cap how many run per day. With technicians:
- Each technician’s home or start location becomes the start of their buckets.
- Add a pre-service stop, such as a parts depot with its own onsite minutes, that every occupied day visits before the first account.
- Choose how the day ends: back home (loop) or at a set end point.
- Travel from home to the depot to the first account is included in that day’s hours, so the cap reflects the real day.
Tell the agent: “Use the three technicians in the technicians layer. Each day starts at home, stops at the Central Supply depot for 15 minutes, then returns home.”
Worked example (sample data)
A two-week HVAC preventive-maintenance book in Houston:
- 280 accounts, mostly every 14 days, a few weekly, and one on hold
- 3 technicians and one shared depot (15 minutes)
- 45 minutes onsite and an 8-hour hard cap
- Day 1 is Monday, November 2, 2026
- Rules: an inventory blackout, a yearly Veterans Day blackout, no Sundays for one site, no Saturdays for another, one fixed inspection, one hard due window, one Tuesday anchor, and one weekdays-only site
The result:
– 42 buckets (3 technicians × 14 days), each holding 5–8 visits
– 279 accounts scheduled; the on-hold account was reported as excluded
Routing the three Day 1 buckets (home → depot → that day’s calls → home) on Azure Maps gave 6.7 to 7.6 hours per technician, including onsite time.
In the same sample, a 300-account version didn’t fit under 8 hours once every technician’s depot stop was counted. That is the kind of capacity answer the tool is for.
What you get back
- Per-bucket facts: day, date (when you gave a start date), technician (when anchored), visits, and estimated hours.
- A visits layer (
<accounts>_visits): one point per scheduled visit, withschedule_day,schedule_date, andbucket_id. An account visited twice appears twice. - A distribution summary: hour spread across buckets, horizon fit, missed due dates, and excluded accounts.
- A downloadable file of every visit row.
Follow-ups that work in one step:
– “Color the visits by day.”
– “Route bucket d01-b1 as a loop from Marcus’s home through the depot.” The agent filters the visits layer by bucket_id.
Schedule hours vs route hours
Bucket hours are a planning estimate: straight-line travel between that day’s stops plus onsite time. When you route a day, analyze_routes reports road drive time, and the two numbers will differ. Use bucket hours to size the plan and route hours for the day itself. Never add them together.
Changing a schedule
Re-run with the same visits-layer name to replace a schedule, or use a new name to keep two side by side for comparison. There is no move-one-visit tool. Change the inputs and re-run.
What it doesn’t do (yet)
- It doesn’t decide how many technicians you need, or where to base them. Test alternatives by re-running with different technician lists or daily caps. Use
cluster_pointsorauto_buildwith a workload target to estimate headcount. - It doesn’t model overnight travel or hotel relocation.
- It doesn’t export to a specific work-order system. Use the visit file or GeoJSON.